a newly installed permeable-paver driveway
Steps // How to Install a Permeable-Paver Driveway
1 ×

Test the Soil and Excavate

 
Step One // How to Install a Permeable-Paver Driveway

Test the Soil and Excavate

excavating a new driveway with a backhoe
Photo by William Wright

First, call 811 for an underground utilities check. Next, do a percolation test to see how fast the soil absorbs water. (Contact your local Cooperative Extension office for details.) Remove the existing pavement, and dig to a minimum depth of 15 inches, unless the perc rate is less than 0.52 inches per hour. In that case, you may need a deeper base or drainage pipe.

 
2 ×

Prepare the Base Layers

 
Step Two // How to Install a Permeable-Paver Driveway

Prepare the Base Layers

unloading gravel into a new driveway for the base layer
Photo by William Wright

Cover the excavation with a 6-inch layer of ¾- to 2-inch washed crushed stone, which has sharp edges that knit together. (River gravel, with its rounded profile, is unacceptable.) Go over it twice with a plate compactor, across and lengthwise. Top with one 4-inch layer of ¼- to 1½-inch washed crushed stone, and compact that twice, too.

 
3 ×

Screed the Bedding Layer

 
Step Three // How to Install a Permeable-Paver Driveway

Screed the Bedding Layer

screeding the gravel to keep it flat for a new driveway
Photo by William Wright

Install a concrete or hard-plastic edging to keep the pavers from shifting. Then, starting from one corner, lay two 2-inch-diameter steel pipes about 6 feet apart and parallel on the compacted base. Cover them with ¼-inch stone, then pull a 2x4 screed board over the pipes to create a flat bed for setting the pavers. Lift out the pipes, fill the gaps, and repeat across the remaining area.

 
4 ×

Place the Layers

 
Step Four // How to Install a Permeable-Paver Driveway

Place the Layers

placing concrete permeable-pavers for a new driveway
Photo by William Wright

Starting at the lowest corner, set the pavers on the bedding layer, tight to the edging and one another. (Nibs on the sides of the pavers automatically create the drainage gaps.) Check every 6 to 10 feet to make sure the pavers are square to the first row. Place all the full-size pieces, then go back and cut pieces to fit in any gaps along the edges.

 
5 ×

Fill the Joints

 
Step Five // How to Install a Permeable-Paver Driveway

Fill the Joints

sweeping gravel into the paver cracks for a new driveway
Photo by William Wright

Once the pavers are in, sprinkle ¼-inch stone, the same used in Step 3, on the surface, and sweep it into the gaps with a wide push broom. Push the broom diagonally across the grid so that you don't dislodge any stones already in the joints.

 
6 ×

Tamp

 
Step Six // How to Install a Permeable-Paver Driveway

Tamp

tamping the permeable-pavers with a plate compactor for a new driveway
Photo by William Wright

Sweep the surface clean, then run a plate compactor diagonally over the entire driveway. The machine's vibrations pack the pavers firmly into the bedding layer and lock them in place. Refill joints that have settled deeply, and compact again. Now your driveway is open for business, rain or shine.

 

Shop Related Products

 

Sponsored Stories

TV Listings

Find TV listings for This Old House and Ask This Old House in your area.