Project details
Skill
3 out of 5ModerateRequires mid-level carpentry skills.
Cost
starting at $100 to $200 per linear foot
Estimated Time
8 to 10 hours in an average-size kitchen
Installing new kitchen cabinets
- Check the ceiling for level in two directions. If it’s out of level, find the low spot and use it as the measuring reference point.
- Measure down from the ceiling (or low spot) 33 inches in several places and mark the walls. These marks represent the bottom of the upper cabinets.
- Connect the marks with a long level and a sharp pencil to produce a level line along the kitchen walls.
- Mark the stud locations on the walls, then measure and transfer stud locations to the back of the upper cabinets. (If you prefer to proceed with one cabinet at a time, begin with the one that will hang in the corner of the kitchen, and continue with consecutive cabinets.)
- Pre-drill a screw-shank clearance hole through the cabinet backs at each stud location.
- Unscrew and remove the cabinet doors; place the doors in a nearby room for safekeeping.
- Hold the first wall cabinet in place in the corner of the kitchen. Be sure the bottom of the cabinet is even with the level line marked in Step 3.
- Drive one screw through the upper back of the cabinet and into the wall stud.
- Check the cabinet for plumb with a level. If necessary, slide shims behind the cabinet. Then drive in the remaining screws to secure the cabinet. Trim the shims with a utility knife.
- Repeat the previous six steps to install the rest of the upper cabinets.
- To prepare for installing the base cabinets, lay a 6-foot level on the floor in several places to identify the high spot.
- From the floor’s high spot, measure up 34½ inches and mark the wall.
- From that mark, draw a level line around the kitchen walls. This line represents the top of the base cabinets.
- Install the sink base cabinet first, centering it under the window.
- Drive shims under the sink cabinet, if necessary, to raise it flush with the 34½-inch reference line marked on the wall.
- Fasten the sink base cabinet to the wall studs with 3-inch screws. Before fully tightening the screws, slip a shim behind the cabinet to fill any void.
- Check the cabinet for level from front to back; slide shims under the front of the cabinet, if necessary, to level it. Trim the shims with the utility knife.
- Install the remaining base cabinets in a similar manner.
- To secure peninsula or island cabinets, screw 2×4 blocking to the floor. Set the cabinets over the blocking, then screw through the toekick and into the blocking.
- Cover the exposed end of the cabinets with a decorative panel. Drive in short screws from inside the cabinet.
- Install all the drawers and doors.
- Fabricate a filler strip to fit alongside the base cabinet that abuts the range. Fasten the filler by screwing through the cabinet face frame.
- Once the base cabinets are installed, make a template for the new countertop.