SUZANNE B
flooring or walls first?

Bought a house that is roughed out inside. Do I lay floors first or sheetrock first? Does it matter other than messing up the floors with sheetrock dust?

A. Spruce
Re: flooring or walls first?

Finished floors will always be the last thing you do. Get all your electrical and plumbing dealt with, finish the walls, then install doors. I would be inclined to paint at this point, then install cabinets. Floors can be done before or after cabinets, your choice.

pgc555
Re: flooring or walls first?

Get your drywall finished and at least primed before you do your tile

dj1
Re: flooring or walls first?

That's right: drywall first. Don't sit the drywall on the floor, hang it about 1/2" higher than the floor.

HoustonRemodeler
Re: flooring or walls first?

When possible we like to get the paint on the walls then install the hard flooring, then install the trim / baseboards. You'll get a neater final product if you can keep the subs from damaging the floors.

pgc555
Re: flooring or walls first?

Pierce,
I'm not familiar with your phrase "floor stripping?" Are you talking about hardwood flooring?

daycarelady
Re: flooring or walls first?
dj1 wrote:

That's right: drywall first. Don't sit the drywall on the floor, hang it about 1/2" higher than the floor.

Does drywall have to breathe?? Is that why it should be 1/2" higher then the floor

A. Spruce
Re: flooring or walls first?
daycarelady wrote:

Does drywall have to breathe?? Is that why it should be 1/2" higher then the floor

The gap is to help prevent wicking from slabs or wet subfloor. It also gives carpet a place to key into which helps to lock it in place.

Sombreuil_mongrel
Re: flooring or walls first?
Rickey6967 wrote:

Well dude plumbing and electrical work always first after completed it then you flooring work because it is complicated work dude am i right buddy????

On rough-in: Drains, then (rigid) ducts, then copper supply lines, THEN electrician. Wires are bendy, the aforementioned items are not.
But yeah, in general hold the hardwoods until much later in the process, the exception being kitchens, where cabinets are best delayed until after the hardwood is down, sanded, and has at least a first coat; less risk of bumping the cabinets, which after all are the most expensive item.
Casey

Fencepost
Re: flooring or walls first?

Vacuum the floors immediately before each phase of painting, especially if you're spraying the paint on. This will prevent dust from getting into the paint.

danhabs
Re: flooring or walls first?

If the flooring is hard wood and you are going to stain it i woud do every thing except the last coat of paint so you can clean up the dust and then put your last coat of paint on to finish the reno