Step 15: Position the Second Post

Positioning the second post
Photo: Kolin Smith
«»
Create your stone drainage bed and set the post height. Slide the sleeve onto the post, shim it, and tack it in place. Sandwich the panel between the posts, and position the loose post so that the panel sits level when resting on the lower sleeve blocks. Keep the scrap blocks in place to steady the panel as you make adjustments. Add drainage stone around the post.
Ask TOH users about Fences & Stone Walls

Contribute to This Story Below

    Tools List

    • nylon mason's line and stakes
      Mason line and stakes
    • post hole digger
      Posthole digger
    • hand clamps
      Clamps
    • four-foot level
      4-foot level
    • miter saw
      Miter saw
    • pneumatic brad nailer
      Pneumatic brad nail gun
    • circular saw
      Circular saw (fitted with a rip fence)
    • drill
      Drill/driver (fitted with -inch paddle bit)

    Shopping List

    1. 4×4 pressure-treated posts
    Get them long enough to go below the frost line; at least one-third of each post must be buried.

    2. Cedar 1×6 lumber
    To be ripped to make the post sleeves, stops, and cap rail.

    3. Cedar square lattice
    Get 4-by-8 sheets that can be cut into two panels each.

    4. Self-adhesive flashing to protect the portion of the post set in concrete.

    5. ¾-inch drainage stone

    6. Concrete
    Choose a fast-setting mix.

    7. 1¼-inch exterior grade brad nails

    8. 1-inch trim-head stainless-steel deck screws

    9. 3-inch stainless-steel deck screws

    10. Polyurethane glue

    11. Polyurethane construction adhesive

    12. Painter's tape

    13. Post caps
    Get 5¼-inch post caps to fit over the sleeved 4×4 posts.